Funding locked-in to progress Armidale’s sewage treatment plant

16 May 2024

Armidale’s one step closer to securing an upgraded sewage treatment plant, with design work underway to overhaul the current facility thanks to over $1.2 million being invested by the NSW Government and Armidale Regional Council.

New water infrastructure to help drought-proof Mungindi and deliver water to Ashley

14 March 2024

Mungindi has switched on a new permanent $325,000 water cooling tower to ensure the town’s 600 residents will continue to have safe and high-quality drinking water during weather extremes.

First stage of Parkes water infrastructure revamp complete

14 March 2024

The Parkes community is well on its way to securing future-proof and drought-resilient water services for decades to come as construction wraps up on the first stage of a major water infrastructure overhaul.

Dungowan artefacts returned to Country

6 March 2024

Thousands of stone artefacts found during the Dungowan Dam investigations in northern NSW have been returned to Kamilaroi/Gomeroi Country during a smoking ceremony at the Tamworth Botanical Gardens this week.

Improving Warrumbungle water and sewerage operations

14 February 2023

Water and sewerage operations across the Warrumbungle Shire have been streamlined thanks to a million-dollar upgrade of the telemetry network.

West Wyalong water security project update

6 February 2023

Works are progressing on the upgrades for a secure water supply to improve water pressure in the townships of Wyalong and West Wyalong.

Winburndale Dam upgrade nears completion

25 January 2023

The $16 million Winburndale Dam Flood Security Upgrade is nearing its final stages, with 19 of 25 pre-stressed ground anchors now installed to reinforce the dam wall.

$19 million Gundagai Sewerage Treatment Plant ready to go

12 December 2022

The $19 million Gundagai Sewerage Treatment Plant upgrade has been completed, providing modern sewerage services to the town’s residents and visitors.

One week left for the new Dungowan Dam EIS

30 November 2022

Tamworth and the Peel Valley have one more week to have their say on the New Dungowan Dam and Pipeline Environmental Impact Statement.

No secret pact for water buybacks

16 November 2022

The NSW Government has reaffirmed its opposition to non-strategic water buybacks being used to meet water recovery targets as part of the Murray Darling Basin Plan.

Walcha one step closer to improved water security

31 August 2022

A new 300 megalitre off-stream storage dam at Walcha will provide greater water security and reliability for residents and businesses and to help drought-proof the town’s water supply.

NRAR finds solution to protect natural streams in Moree Plains

8 November 2021

The Natural Resources Access Regulator (NRAR) has helped to protect environmental flows in the Gwydir River system, by finding a solution to address a landholder’s alleged unlicensed water take.